An update through images – The Highbridge Hotel

August 2018 *Cutting of the Sod*

September 12thPiling works are underway

September 21th – Piling works have been completed

September 28th – The sheet piling is underway

October 5th – The footings are being dug.

October 12th – The reinforced steel cages to footings are in.

October 22nd – Work on the footings continues

November 2nd – The concrete for the accommodation block has been poured at our site